Eight projects ran up to 13 years late
Late is normal at this size. Hinkley Point C now targets 2030. Its first target was 2017.
Sources: The Guardian, Severn Estuary Interests Group, Wikipedia, Business Insider, Forbes, E&E News, Luxuo, BBC. Hinkley is a forecast. Kashagan is "more than 8". Crossrail runs Dec 2018 to May 2022.

Delay carries a bill: 14.6x for the Opera House
McKinsey reviewed 300+ projects over $1 billion. Average cost overrun: about 80%. Average schedule delay: about 50%.
Sources: Wikipedia (A$7M to A$102M), FX Design, Luxuo, The Guardian, E&E News, McKinsey. Nominal figures. Hinkley mixes 2016 and 2015 price bases.
US disputes now average $56.0M vs $16.3M in 2018
That is 3.4 times higher. Delays and time extensions are now a top-3 cause of disputes.
Arcadis expects more disputes in 2026. The average dispute lasts 12.2 months vs 17.6 in 2019.
Source: Arcadis, 16th Annual Construction Disputes Report, US edition, 2026.
What a delay analyst does
A project planned one finish date. It hit a later one. The analyst finds which events caused the gap, and whose they were.
Then the gap gets a price. That is where claims and arbitration start.
Sources: Secretariat; AACE RP 29R-03.
Learn it on a road trip
Our own trip plan said 5 hours. The road disagreed. Taking 9 hours is a 4-hour delay.
The road closure lasted 3 hours. The flat tire lasted 2. They overlapped for 1, so together they cost 4 hours, not 5.
Illustration with invented numbers. The critical path is the chain of tasks that sets the finish date.
Nine ways to ask the same question
AACE lists nine methods. Some read the schedules that exist. Others rebuild a schedule and test it.
Read the schedules
Static: compare two pictures
- 3.1Plan vs actual, in one go
- 3.2Plan vs actual, period by period
Dynamic: follow the updates
- 3.3Windows: step through each update
- 3.4Windows with the causes split
- 3.5Windows with missing updates rebuilt
Rebuild and test
Additive: put the delays in
- 3.6Add delays to the plan
- 3.7Time impact: add them one at a time
Subtractive: take the delays out
- 3.8Remove delays from what happened
- 3.9The same, window by window
The SCL Protocol, second edition, lists six methods. It prefers none.
Sources: Long International, ScheduleInsight, 5 Mar 2026. AACE RP 29R-03, rev. 2011.
One hour, two owners. Who pays?
That purple hour had two causes at once. Experts call it concurrent delay.
One expert paper says methods 3.1 to 3.5 usually handle it poorly. It adds that in most US jurisdictions, neither side then typically gets delay damages.
The method you pick decides how that hour is counted.
Source: Long International, "AACE 29R-03 Schedule Analysis Methods".
No updates, no windows
Windows analysis needs a full set of credible schedule updates. Without them, that method is off the menu.
Arcadis respondents rank accurate, timely schedules second for settling disputes early.
Size matters too. The SCL Protocol says the method must fit the amount in dispute.
Sources: ScheduleInsight; Arcadis 2026.

In the Gulf, big builds open in phases
Barakah Unit 1 began commercial operation in April 2021. Units 2, 3 and 4 followed in 2022, 2023 and 2024.
Dubai Metro's Red Line opened on 9 September 2009 with 10 of 29 stations. Jebel Ali station followed on 11 March 2011.
Each section can carry its own completion date. So each can carry its own delay.
Sources: Energy Institute, EWEC, Wikipedia.
New tools, same basics
Arcadis found owners, contractors and advisors investing in digital tools and AI to manage risk.
Its warning: new tools bring new problems when poorly used. Disciplined fundamentals still decide outcomes.
On 23 July 2026, Secretariat and ACEDS reported near universal AI use across the legal industry.
Sources: Arcadis 2026; Secretariat and ACEDS AI Report 2026.
What it means for the market
- More disputes are expected in 2026.
- Delay is now a top-3 cause of US disputes.
- Average value: $56.0M vs $16.3M in 2018.
- Records decide which methods an expert can use.
Read every big project as a plan, a record and a price tag.
Late is the norm
Only 8.5% of 16,000 projects hit both cost and schedule targets. Delay analysis decides who pays for the rest.
Up to 13 years late
Eight projects across buildings, infrastructure, power and oil and gas. Hinkley Point C now targets 2030, not 2017.
Delay carries a bill
The Opera House cost 14.6 times its first estimate. Hinkley Point C stands at 1.9 times and is still building.
The bill goes to dispute
The average US dispute was worth $56.0M in 2025, vs $16.3M in 2018.
Enter the delay analyst
One job: find which events moved the finish date, and whose they were.
A road trip explains it
Five hours planned, nine taken. Two problems overlapped for one hour.
Nine methods, one question
Some read the schedules. Others rebuild one. No single method is preferred.
One hour, two owners
Concurrent delay is where methods disagree. The choice of method decides who owns that hour.
Records pick the method
No contemporaneous updates means no windows analysis. Project controls today set the options tomorrow.
Closer to home
Barakah and Dubai Metro opened in phases. Each phase can carry its own delay.
New tools, same basics
AI is spreading fast. Arcadis says disciplined fundamentals still decide outcomes.
What it means
More disputes, bigger disputes, and delay as a top-3 cause. Records decide the method.